August 15 → September 29 2019

Notice of Study Completion and Public Review Period

The Environmental Study Report (ESR) for the Thompson Road EA is now complete. The ESR is available online and at Town Hall (Engineering Services - 2nd Floor, 150 Mary Street) for a 45 day public review period.
February 2019

Comments and Questions Are Now Officially Closed

Thank you for your interest and input into this important Town of Milton Project. The comment and question period is now closed. All comments will be considered and documented as part of the final Environmental Study Report (ESR) for the project, and answers to specific questions posted in the Q&A section have been provided. The final ESR is anticipated to be completed by the end of Q1 2019, and once the ESR has been filed for public review, a notice will be posted on this page advising the public where it can be viewed. If you have any further questions or comments please do not hesitate to contact the Engineering Department at engineering@milton.ca or 905-878-7252 x2500.

December 13 2018

Comments Deadline

Residents are encouraged to submit comments about the Municipal Class Environmental Assessment (Class EA) Study for the road improvements on Thompson Road, between Louis Saint Laurent Avenue and Britannia Road.